About Global Documents
Global Documents provides you with documents from around the globe on a variety of topics for your enjoyment.
Global Documents utilizes edocr for all its document needs due to edocr's wonderful content features. Thousands of professionals and businesses around the globe publish marketing, sales, operations, customer service and financial documents making it easier for prospects and customers to find content.
Copyright 2009 AACE, Inc.
AACE International Recommended Practices
AACE International Recommended Practice No. 36R-08
DEVELOPMENT OF COST ESTIMATE PLANS
AS APPLIED IN ENGINEERING, PROCUREMENT, AND
CONSTRUCTION FOR THE PROCESS INDUSTRIES
TCM Framework: 7.3 Cost Estimating and Budgeting
Acknowledgments:
Gregory C. Sillak (Author)
Bruce E. Bradley
Keith R. Didriksen
Fabiana Francis, PSP
Dr. Paul D. Giammalvo, CCE
Ambrish Gupta
John K. Hollmann, PE CCE CEP
Carlton W. Karlik, PE CEP
Christopher L. Kinney
Paul S. Kupakuwana
Paratharajan N. Pille
L. Ron Rowland
Terence M. Stackpole
T. Mac Sumrall, CCC
David A. Williams, CEP
Charles P. Woodward, PE CCE CEP
Joseph Yang, CCE
Nor Y. Yazid
James G. Zack, Jr. CFCC
Copyright 2009 AACE International, Inc.
AACE International Recommended Practices
AACE International Recommended Practice No. 36R-08
DEVELOPMENT OF COST ESTIMATE PLANS AS
APPLIED IN ENGINEERING, PROCUREMENT, AND
CONSTRUCTION FOR THE PROCESS INDUSTRIES
TCM Framework: Reference 7.3 Cost Estimating and Budgeting
June 12, 2009
INTRODUCTION
Purpose
This recommended practice (RP) of AACE International (AACE) is a guideline for development of cost
estimate preparation plans for engineering, procurement and construction (EPC) projects in the process
industries.
The purpose of a cost estimate preparation plan (herein referred to as "estimate plan") is to establish and
communicate how the preparation, development, review and approval of the estimate will be completed.
Background
AACE International's Total Cost Management (TCM) Framework[4] section 7.3.2.1 "Plan for Cost
Estimating and Budgeting" highlights the need to develop estimate plans. This RP delineates industry-
specific practices for development of an estimate plan as they are applied to EPC projects in the process
industries. (A future AACE International RP will provide a guideline for development of a generic cost
estimate plan.)
Cost estimating in the hydrocarbon processing industries (e.g.; chemical, refining, petroleum production
facilities, etc.) has evolved to a relatively advanced state over more than four decades of application.
These industries have developed many common practices and identified industry-specific best practices
through benchmarking and knowledge-sharing. The practices reflected in this document are a result of
compiling notes made by industry practitioners, lessons learned and publicly available documents.
Scope
With reference to the TCM Framework, this document addresses the steps before and after the "Plan for
Estimating and Budgeting" step to the extent necessary for an effective estimate plan.
This document is primarily focused on estimates prepared for project sanction purposes of land-based
facilities. Typically, project sanction is based on a Class 3 estimate. Estimate plans for other classes of
estimates may be adapted from this document.
The basic principles are applicable to all contracting strategies and asset owner (herein referred to as
"owner") configurations. For example, contracting strategies may be in the form of reimbursable
engineering with fixed price procurement and construction and/or EPC alliances, etc. Owner
configurations may include self-perform, partnerships with a named "operating company" or consortiums
responsible for managing the project/program and so on. Some key principles are:
Preparation of an estimate plan helps to ensure successful estimate completion in an effective
and timely manner.
Engaging key stakeholders in the estimate planning process prior to the start of the estimate
development process, improves the likelihood of meeting estimate objectives.
The estimate plan defines what information is required from who and when.
An approved estimate plan provides a duly authorized basis to proceed with the estimating effort,
clarifies requirements and responsibilities.
RPRP
Copyright 2009 AACE International, Inc.
AACE International Recommended Practices
Development of Cost Estimate Plans As Applied in Engineering, Procurement, and
Construction for the Process Industries
June 12, 2009
2 of 24
RECOMMENDED PRACTICE
This recommended practice is divided into three main sections:
1. The Estimate Development Plan Process defines the main steps and discusses issues to be
considered in preparing an estimate plan.
2. The Estimate Plan Format and Content provides a suggested format for an estimate plan along
with annotations. It is designed to allow practitioners to use and modify it as needed for their
specific situation.
3. Appendices contain sample formats which are used in conjunction with the estimate plan.
ESTIMATE DEVELOPMENT PLAN PROCESS
Figure 1 illustrates a summary of the estimate development plan process.
Figure 1. Estimate Plan Development Process
Inputs to Estimate Plan Development
It is recommended that owners furnish specifications for estimate plans within the contract or prior to the
contractor(s) preparing an estimate plan. In any case, the onus is with the lead estimator of each
organization to develop an estimate plan which will satisfy the owner's needs. Where multiple contractors
are involved, the owner is ultimately responsible to ensure that all organizations involved are properly
coordinated in terms of scope delineation, estimate delivery timing and consolidation. In cost
reimbursable situations, owner agreement on how the estimate will be prepared before developing the
estimate is crucial. If this is not done, accusations of wasting the owner's money may be directed toward
the contractor and it may result in the owner's refusal to pay for the "wasted effort". It is not only important
in terms of keeping good client relations but also in terms of helping to ensure the owner has properly
Prepare Draft
Estimate Plan
Estimate Plan
Reviews
Estimate Plan
Approval
Estimate
Development
Process
Inputs
Owner estimate requirements including accuracy
& review/approval timing
Contractor review/approval process(es)
Project scope & strategy basis including
alternative scenarios & known site conditions
Schedule from prior phase
WBS, code of accounts, estimate formatting and
work packages or work packaging basis
Risks & opportunities from prior phase
Lessons learned from prior phase and projects
Project historical information, estimating tools &
estimating personnel
Updates
Changes
RPRP
Copyright 2009 AACE International, Inc.
AACE International Recommended Practices
Development of Cost Estimate Plans As Applied in Engineering, Procurement, and
Construction for the Process Industries
June 12, 2009
3 of 24
understood and clarified what is required. Mature project management organizations have appropriate
estimate review processes in place to provide executives with an understanding of the estimate variability
(risks, uncertainty, etc). Buy-in up front from the owner saves valuable time at the end of the estimating
cycle when the owner project team is under pressure to deliver the estimate to their management.
Ideally, the owner estimator only needs to verify that the contractor performed what was agreed
beforehand and conduct a final benchmarking analysis of the results before recommending approval to
owner project management. Contractor completion of an estimate is only the beginning of the owner's
approval process, therefore it is critical, regardless of contract form, to ensure alignment on timing of
estimate review and delivery requirements at the outset. Owner organizations typically have
predetermined dates when board meetings are held and their agendas are set several months in
advance. Larger projects tend to be separate agenda items. Delays in the estimating process may cause
the project to miss a critical window of opportunity. For smaller projects, the timing and process for owner
annual budgeting decisions need to be understood.
Despite all the effort that goes into cost estimates and the resulting volume of documentation for project
sanction, estimates are usually summarized into a single line input to project economics in the form of a
cash flow. The basis for the time-spread of cash flows must be given careful thought when prepared, and
adequate scrutiny when reviewed. Some organizations designate cash flow development as a function of
scheduling due to the interrelationship between activity timing and costs. In any case, it is advisable to
assign this important task to an experienced person who is knowledgeable in how invoices are paid
relative to work completion and areas where the schedule may not contain activities which reflect
significant cost items. For example, insurance premiums, typical payment terms for large value
equipment (prior to knowing actual terms), or the fact that "variable indirects" tend to be front and back
loaded rather than spread evenly over time. Cash flows developed without adequate analysis and/or
hastily under tight time pressures to support project approval processes may result in economic projects
being cancelled or uneconomic projects being approved. Cash flows are also used for determining
escalation and are therefore a key deliverable to be identified in estimate plans. Owners using the
accrual-based accounting method usually require a cost flow (incurred cost timing) in addition to cash
flow (payment timing). Costs are typically incurred about two months earlier than they are paid but it
varies significantly depending on owner and contractor procedures as well as vendor invoicing habits.
The necessity of an incurred cost flow to accompany the estimate should be clarified prior to completion
of the estimate plan.
Updated scope and project execution plan information are critical to planning estimate development. The
project execution plan describes contracting strategies, work schedules/shifts/overtime, labor sources,
fabrication and modularization, and so on. Checklists are an effective aid to ensure portions of scope are
not omitted. A more advanced approach is to ensure that the estimating deliverables and controlling
documentation are identified for each portion of scope and corresponding execution plans.
The most current schedule information is needed to analyze resource requirements and peaks in addition
to any weather windows, planned outages, tie-in opportunities, etc. This may include potential cost
impacts of plans to perform work less efficiently than normal, or constraints, or innovation.
Estimate data (quantities, hours, costs) should be coded in a manner that considers how the estimate is
prepared (including related source data), reviewed (including benchmarking) and how it will be used for
cost control. Recasting an estimate consumes valuable resources and poorly formatted estimates may
result in situations where the control team takes several months to establish control. The contractor may
need to submit its project code of accounts to the owner for development of cross-reference mapping to
owner's code of accounts. The contractor may be required to provide summarization of project costs
according to owner-specified formats. Any other special requirements must be considered such as: pre-
investment cost breakout; property tax cost breakout; separation of facility ownership values; asset
valuation; asset financial value depreciation and income tax classes; final cost report formats; partner
reporting requirements; currency conversions; etc.
Risks and opportunities from the prior phase and any updates should be addressed (mitigated, accepted,
etc.) such that their disposition is known for the follow-on estimating and risk analysis. Ideally, this is
RPRP
Copyright 2009 AACE International, Inc.
AACE International Recommended Practices
Development of Cost Estimate Plans As Applied in Engineering, Procurement, and
Construction for the Process Industries
June 12, 2009
4 of 24
done in an aggressive manner to improve the chances of producing a good estimate and project
success.
Lessons learned from the prior phase can be a source of opportunities to reduce costs or highlight
significant gaps in past practices which need to be addressed prior to completing the estimate. Any
assumptions that can be removed or clarified should be.
Stating the planned sources of estimating basis such as project historical data is important for obtaining
owner and contractor alignment and confirming validity. This also applies to the estimating tools,
processes, and estimator qualifications.
In summary, all inputs to the estimate and required outputs should be identified and included in the
estimate plan. If requirements are not clear, meetings should be held to outline the estimate planning
process and obtain alignment.
Prepare Draft Estimate Plan
A draft estimate plan is prepared based on all the inputs available including any related clarifications. If
the estimate is to be delivered as part of a larger package which includes other deliverables such as the
scope document, engineering design basis, schedule, execution plan, risk analysis, etc., it should be
reflected accordingly within the estimate plan.
The level of project definition and facility process complexity will have a significant impact on estimate
plan content and volume. For example, a project with a mine or subsurface components, several
processing units, storage facilities, offloading/export facilities, and pipelines will require much more
documentation than a project to install a single process unit or replace a piece of equipment. A multiple
small projects environment where facilities are installed and estimated on a routine basis, may require
less formality and planning than suggested by this guideline if executed by a team of people who have
done so together over several years.
Publishing a team contact list with the estimate plan and/or as part of an estimate responsibility matrix is
recommended.
Word-processing software is best suited for documenting the estimate plan. It can be supplemented with
spreadsheet software for more complex tables and numerical/date information management. For
complex projects, scheduling software is suggested for planning the specific work activities necessary to
complete the estimate including the estimate plan, estimate basis, and deliverables to estimating. The
estimate planning and development activities should be an integral part of the project schedule for that
phase.
Estimate Plan Reviews
Once a draft estimate plan and corresponding schedule are complete, a set of review meetings are held
with all key stakeholders to communicate any defined requirements and responsibilities. It is imperative
during this review that everyone with a key deliverable commits to meeting their assigned dates or else
the entire plan will be in jeopardy of slipping, including the final due date to the owner. Issues and
concerns relative to the estimate plan are documented along with plans to resolve them.
Estimate Plan Approval
Once an estimate plan is satisfactory to the owner, the authorized owner and contractor representative(s)
should endorse it with signatures to indicate alignment and approval. Preferably, this occurs after other
key stakeholders have signed to indicate buy-in and committed to be accountable.
RPRP
Copyright 2009 AACE International, Inc.
AACE International Recommended Practices
Development of Cost Estimate Plans As Applied in Engineering, Procurement, and
Construction for the Process Industries
June 12, 2009
5 of 24
Upon approval of the estimate plan, roll-out sessions are held to communicate the approved basis for
proceeding with estimate development.
Estimate Development Process
A good estimate plan will make the estimating process more efficient. If conditions change significantly,
updates to the estimate plan are necessary to maintain alignment. Changes are integrated and dealt with
through the project change management process.
The final version of the estimate plan may be used as the starting point for the basis of estimate by
carrying over common elements and wording from the estimate plan. Preparation of the basis of estimate
document while the estimate is being prepared is preferred to completing it after the estimate when time
is short and key information may have been forgotten or gone missing along with personnel that are no
longer available.
ESTIMATE PLAN FORMAT AND CONTENT
The extent to which each of the sections below can be completed as indicated is highly dependent on the
level of definition available. Since it is a recommended practice to define as much of the project as
possible up front, that is assumed to be the case. It may be necessary to explain what information is not
available at the time of estimate plan preparation, when it will be available and how it will be handled.
Alternatively, there may be a plan to update the estimate plan at an appropriate point before substantial
work is done on the estimate. Be aware that if several "workarounds" are planned, it may be a sign there
is misalignment between available project definition and estimate objectives.
Purpose of Estimate
The purpose of the estimate sets the focus for the remainder of the document. Summarize what the
estimate will be used for and by who. For example, describe the overall facility type and location. Identify
whether the estimate is a part of requirement for approval to proceed to the next phase of the project
(i.e.: AFE, company-specific stage gate, etc.), a special study, to update the cost control baseline and so
on. Secondary purposes are to establish a basis for project control, to quantify resource requirements
and provide owner decision-makers with an appropriate level of confidence in the estimate.
Based on level of project definition, state the expected accuracy range and AACE International Estimate
Class[7]. (E.g.: It will be a Class 3 estimate and the final cost is expected to be within -10% to + 15% of
the estimate after applying contingency.)
Key Estimate Development Milestones
As discussed above, the estimate plan activities should be an integral part of the project schedule for that
phase. The detailed estimate plan schedule is discussed later in the document. A table of the key
deliverables and planned dates based on the detailed schedule of the estimate plan should be prepared
for management summary purposes. The table may be expanded to contain details such as the expected
status of each deliverable or an estimator site visit. Table 1 is provided as an example. The table may be
extracted for reporting estimate development status to management by adding a column for actual date
completed.
RPRP
Copyright 2009 AACE International, Inc.
AACE International Recommended Practices
Development of Cost Estimate Plans As Applied in Engineering, Procurement, and
Construction for the Process Industries
June 12, 2009
6 of 24
Milestone
Date
Estimate plan approval
ddMMMyy
Agree estimating basis with owner (software, methodology, labor productivity, labor rates,
equipment/material pricing, MTOs, allowances, indirects, engineering, scope allocation)
Scope cut-off date for estimate
This is when key engineering and execution basis documents are frozen for estimating
purposes. (e.g.: PFDs, P&IDs, equipment list, piping line list, electrical single-line diagram,
specifications, instrument index tie-in list). Some may be available earlier than others but
none should be after the cutoff date to maintain a consistent basis.
MTO's issued to estimating (expand by discipline and WBS as required)
Engineering, fabrication and construction hours provided for planning/scheduling
Execution schedule and labor profiles input to estimating
Contractor (or integrated EPC/owner) risk analyses complete
Contractor corporate review/approval of estimate (if allowed by owner)
Owner project management review of cost estimate, estimate basis and cash flow
Contractor revisions to estimate, basis and cash flow
Owner corporate review of cost estimate
Owner estimate and/or phase gate approval
Final contractor revisions to estimate and cash flow (if required)
Owner cost estimate approval
Cost control base recast issue for approval (for reference)
Cost control base approval (for reference)
Table 1. Examples of Estimate Development Milestones
Project Scope and Execution Plan Summary
Summarize the project scope and execution plan for each project phase and make reference to the
primary documents. Identify each process unit, offsites, utilities, subsurface facilities, etc. Indicate
capacities and any other significant factors such as contracting, fabrication and modularization strategies.
Explain the labor type (union, open shop, mixed, or other) and quantify expected sources (number of
local, travel cards, temporary foreign workers, etc.) Provide an estimated overall progress completion
percentage for engineering at the estimate cut-off point.
Construction, Fabrication, and Operating Parameters
Refer to an authoritative source of average annual weather conditions at the job site along with
maximums, minimums and time of year they occur. Corresponding design basis criteria such as
pressures, amount of alloy materials, minimum and maximum ambient design temperature should be
stated. Known soil conditions are summarized (e.g.: clay/rock, topsoil depth, permafrost, water table,
underground aquifers, etc.) Distance to nearest major population centers, infrastructure availability, and
distances are worth stating.
Project Execution Schedule Basis
At the estimate planning stage, a summary execution schedule (by facility, phase, unit, and
commodity/discipline) is included with the estimate plan. Any special schedule events that impact costs
are shown on the schedule and/or described further in the narrative. Examples are: weather windows
(shipping and site); operating plant outages; tie-ins: shift work; extended overtime; union contract
RPRP
Copyright 2009 AACE International, Inc.
AACE International Recommended Practices
Development of Cost Estimate Plans As Applied in Engineering, Procurement, and
Construction for the Process Industries
June 12, 2009
7 of 24
expiration dates; peak manpower periods; planned downtime (e.g.: holidays, planned evacuations in
existing facilities); and known and pending regulatory/environmental issues.
Estimating Methodology
Cover items such as estimate type (capacity ratio, equipment factored, detailed, etc.) Refer to the
expected accuracy range stated in the purpose section and summarize how it will be accomplished with
any applicable discussion of risk analysis to be completed.
Estimating Software
Describe all software and versions to be used including how it is to be used. (E.g.: simulated quantities,
internal database, interface software to load productivity rates into estimating program, etc.)
Coding and Formatting
Attach project code of accounts and project work breakdown structure (WBS) or other specified coding
and formatting requirements as an appendix to the plan or refer to it. The formats to be used in
presentation of the estimate should be clearly identified and agreed with the owner before starting the
estimate. This includes the detailed and summary forms. The cost estimate must show all calculations.
Quotes from vendors and in-house cost databases do not necessarily need to be included with the
estimate but should be referenced and available for viewing by the owner throughout the life of the
project. As a minimum, the detailed forms will contain quantities, unit of measure, hours per unit, labor
hours, labor cost per hour, labor cost, material cost per unit, material cost, equipment cost per piece, and
total equipment cost. Subcontract units, hours, and costs should be broken down in the same manner to
determine camp space (if applicable) and worker densities.
Cost estimate summaries may be specified by the owner. Costs for each inside battery limits (ISBL)
process unit as well as outside battery limits (OSBL) costs should be separated. Allocation of indirect
costs to each ISBL unit and OSBL unit for estimating purposes depends on the execution strategy. If a
single contractor is involved with more than one process unit, then indirect costs should be separated by
the contractor. If a contractor is only responsible for one process unit, the indirect costs will be part of the
total costs for that unit.
Filing Structure
The estimate material including all backup is to be primarily filed and maintained according to the WBS
and code of accounts referenced in the Coding and Formatting section. Other information is to be filed
according to the format of the estimate basis. Additional sections may need to be created for the
following:
Request for Proposal
Review Comments and Minutes
Competition
Drawing List
Addenda
Miscellaneous
Units of Measure
State the type of units of measure (i.e.; metric, imperial) and any exceptions that may apply.
RPRP
Copyright 2009 AACE International, Inc.
AACE International Recommended Practices
Development of Cost Estimate Plans As Applied in Engineering, Procurement, and
Construction for the Process Industries
June 12, 2009
8 of 24
Currency and Exchange Rates
State the currency to be used (e.g. US Dollars - USD). Indicate the exchange rates for foreign purchases
as applicable.
Process Equipment Pricing
Indicate expected rough percent of equipment costs to be based on budget quotes, firm bids, in-house
pricing or other basis. This varies depending on desired estimate accuracy and level of engineering
development. A summary of the bidding process may be included such as minimum number of bidders,
how bids are normalized for evaluation purposes including exchange rate basis of foreign currencies and
bid validity periods. The planned method of estimating shop inspection, testing, witnessing, and related
travel requirements should be described. Identify whether electrical and instrumentation/automation
equipment are covered under the respective bulk commodity material sections. This should be consistent
with the coding/formatting requirements. Freight and vendor representatives for construction,
commissioning, and start-up should be separately identified whether or not they are part of the equipment
account. Specify whether ladders and platforms will be included with the equipment, "dressed" onsite or
offsite and other similar clarifications. E.g.: equipment insulation is in bulk materials if not supplied by the
equipment vendor. Provide a current version of the equipment list with targeted items for firm quotes
identified. A "priced equipment list" should be specified as an estimate deliverable. Discuss how any
design allowances for equipment will be developed such as guidance from the discipline specialists,
project execution and procurement personnel. Design allowances for equipment are discussed here and
included with the table of bulk commodity material allowances shown in Appendix A.
Spares
Spares require consideration of financial accounting rules and operating philosophy. This includes freight
for spares when practical to separate.
Capital spares should be identified by individual piece of equipment. Refer to owner definition of capital
spares.
Explain the basis for estimating commissioning and start-up spares such as vendor recommendation or if
it will be done by the start-up team. Refer to owner definition of commissioning and start-up spares.
Operating spares and initial stores stock inventory should either be identified as excluded or included as
directed by owner. Agreement with the owner accounting controller is advised regarding categorization of
spares, initial stores stock, and non-capital expense ("OPEX") versus capital ("CAPEX").
Describe how the costs will be determined for each type of spare such as historical data, reference data
and/or discussion with discipline specialists or experts.
Non-Process Equipment Pricing
Refer to the project code of accounts as a guide for segregation of process equipment versus non-
process equipment purchased for use during operation of the permanent facilities. Mobile equipment
(front-end loaders, bucket wheels, excavators, etc.); rolling stock (rail locomotives, cars, etc.); cranes;
personnel vehicles (cars, vans, busses, etc.); maintenance vehicles (flat bed, fork lift, man lift, bundle
pullers, etc.); emergency vehicles (fire truck, foam wagon, ambulance, etc.); fire protection and safety
equipment (extinguishers, hose reels, etc.); lab equipment; office computers; supply boats; and so on.
RPRP
Copyright 2009 AACE International, Inc.
AACE International Recommended Practices
Development of Cost Estimate Plans As Applied in Engineering, Procurement, and
Construction for the Process Industries
June 12, 2009
9 of 24
Vendor Representatives
Identify separately vendor representatives estimated for each piece of equipment or tagged item. If it is
an overall allowance then state the basis for the allowance.
Bulk Commodity Material Quantities
For each commodity, describe the methods to be used such as: detailed material take-offs, based on
sketches, standard detail designs, computer-simulated take-offs, or factored. The extent of planned input
from vendors, discipline specialists/experts and project execution personnel should be stated. The
portion of quantities expected to be available from a 3D computer design model are provided as
applicable for each commodity. Examples of further details needed to adequately explain quantity basis
for each commodity are provided in Appendix C. A table summarizing the planned quantity development
and take-off basis for each commodity can be a helpful quick reference as shown in Appendix B.
Bulk Material Quantity Take-Off Allowances (Design Development Allowance)
Material take-off allowances are based on an estimate of the known but undefined quantities. For each
commodity, describe the rationale for estimate allowances in relation to the level of engineering definition
and the methods to be used to develop quantities. A table listing the estimated allowance for each
commodity and percentage of the base is to be included for quick reference. Refer to Appendix A.
Bulk Material Construction Waste Allowances
Explain the basis to be used for construction waste allowance (e.g.: discussion with specialists, historical
data) by commodity. For quick reference, this is shown with design development allowances in a
summary table. Refer to example in Appendix A.
Bulk Commodity Material Pricing
Indicate expected percent of bulk material costs which will be budget quotes, firm quotes, in-house
pricing or other sources. Include basis for equipment (process, non-process, electrical, instrumentation)
shop inspections and testing. Separately address material supplied to fabricators and material for site
installation. A table could be used to summarize this as well.
Address any special considerations such as whether a concrete batch plant will be used at site.
Offsite Fabrication
The planned amount of offsite fabrication of bulk materials (if available) and the estimating methodology
should be explained (e.g.: unit rate, by weight, by pipe class, fabricator quotes, etc.)
Offsite Module Assembly
Describe the extent of offsite module assembly planned to be done and the geographical locations of the
assembly facilities. Briefly discuss whether modules are placed directly on foundations or at an interim
staging area for further work to be done before moving to final location. Provide the basis for estimating
module yard labor hours and cost rates. Address assembly of pipe rack modules and equipment modules
here. Equipment purchases and "skid packages" are covered under equipment.
RPRP
Copyright 2009 AACE International, Inc.
AACE International Recommended Practices
Development of Cost Estimate Plans As Applied in Engineering, Procurement, and
Construction for the Process Industries
June 12, 2009
10 of 24
Freight
Cost of freight for process equipment should be identified separately from other freight. Indicate how
domestic freight for bulk material will be calculated. Describe availability and pricing source of special
module transportation equipment and other "heavy hauls". Reference the discussion above regarding
placement of modules directly onto foundations and impact on freight cost. Foreign freight costs should
clearly state how the ocean-, air-, and land-based shipping are to be priced as well as any export
preparation/crating and applicable duties.
Construction Labor Productivity
Explain how labor productivity will be determined for each commodity and equipment. It should address
items such as: adjustments to a base productivity for labor density, facility complexity, excessive
overtime, weather, shifts, labor quality, labor availability, worker facilities (e.g.: lockers, washrooms,
lunchrooms) proximity to ISBL and OSBL work areas and support facilities (e.g.: tool crib, warehouse,
material staging area), greenfield versus brownfield versus revamp versus shutdown conditions, soil
conditions, elevated work, geographic location, and any other factors affecting productivity. Provide a
description of the base productivity including the types of projects included, such as company USGC, 3rd
party software database, in-house data, etc. A table should be provided in the estimate plan showing how
each factor will be applied and its affect on the rate to be used in the estimate.
Construction Work Week and Overtime
Indicate the construction work week basis and applicable shift schedules (e.g.: 8 hours per day x 5 days
per week.) Explain how overtime hours and related cost allowances will be determined.
Construction Labor wage rates
Describe how crew mixes, union contracts, non-union wages, benefits and other factors will be used to
build-up the labor rates. Obtain a copy of the craft labor agreements when available. Crew mixes
includes portions of apprentices, foremen, general foremen, journeymen. For each commodity, crew mix
also refers to potion of total for each trade (e.g.: pipefitters, welders, carpenters, electricians, etc.)
Construction Subcontracts
It is preferable to quantify all subcontractor hours for construction infrastructure planning and worker
density analysis purposes. Subcontractor materials are to be separately identified as owner, contractor,
or sub-contractor supplied. State the construction strategy pricing basis (unit-price, lump-sum, etc.) for
each subcontract. E.g.: piling based on firm unit rates including aggregate and all embeds but excludes
pile caps and dewatering beyond a predetermined amount; insulation based on budget quotes; painting
is included with steel, pipe and equipment pricing except field touch-up which will be based on in-house
data; and so on.
Construction Indirect Costs
The cost basis for construction indirect costs should be broken down according to the code of accounts
as per the following example:
Construction Management To be developed using a personnel plan by position or by discipline spread
over the project duration. Explain how office and travel costs are covered including courier, temporary
office furniture, office equipment, supplies, computers, and telephone charges. Consider design and
RPRP
Copyright 2009 AACE International, Inc.
AACE International Recommended Practices
Development of Cost Estimate Plans As Applied in Engineering, Procurement, and
Construction for the Process Industries
June 12, 2009
11 of 24
drafting be done at the construction site including as-built drawings. Specify what is part of the as-built
scope e.g.: process flow diagrams (PFD); process and instrument diagrams (P&ID); undergrounds;
junction box wiring diagrams; single line diagrams; load lists; schematics; 3D model updates; etc.
Personnel costs are normally kept separate from office costs in detail cost accounts but they may be
discussed together in the estimate plan. Construction insurance may be included here if it is not covered
by owner project overheads. Bond costs may be included if applicable.
Camp (if applicable) Identify who will stay in the camp and related construction manpower peaks.
Include catering and what is to be part of the price such as lunches for personnel not staying in camp,
whether any utilities (water, gas, power, etc.) are part of the cost. Consider whether it will be pre-fab, built
on site and if personnel will be housed single, double, or otherwise. State amenities to be included such
as laundry facility, exercise room, indoor/outdoor recreation, etc.
Temporary Facilities - Describe onsite or offsite locations for temporary buildings, roads, parking,
laydown areas and material staging, etc. State how requirements for temporary offices and other facilities
will be determined. Document any existing utility facilities available for construction use and/or source.
Utility Consumption It is recommended utility consumption (gas, power, water, sewer) be kept separate
from the related facilities cost for estimating and control purposes. These costs can vary significantly and
may be provided from various sources such as existing plant, temporary facilities, and/or new permanent
facilities. Identify construction power requirements for electric welding machines, warehousing,
construction offices, parking lot lighting and plug-ins, onsite fabrication shops, etc. The same applies for
fuel, gas, potable water, and sewer.
Temporary Services Note any special safety requirements and who is responsible (e.g.: Nomex, gas
sniffers, fire watch, etc.) Weather protection may be based on a percentage of concrete and piping per
historical data. An allowance for general site dewatering will be based on average annual rainfall and
water table data. Drinking water supply source and pricing basis are described.
Construction Equipment Typically, a table is developed showing monthly requirements for cranes, man
lifts, and other construction equipment. Availability and pricing basis to be used for cranes should be
discussed. Describe the number and type of cranes needed for heavy lifts. Include freight/shipping, and
mobilization/demobilization. Include assembly/disassembly if not covered elsewhere.
Small Tools Delineate how cost of small tools is allocated between indirects and subcontractor rates as
applicable. A brief discussion of the source (e.g.: tool crib rental, purchase, etc.) should be included.
Refer to any definition of small tools. Discuss small tool replacement and repair requirements.
Scaffolding Explain whether scaffolding labor will be factored from specific direct accounts based on
historical data and adjusted for height in conjunction with discussion with construction specialists.
Scaffold material requirements basis is provided by construction and/or historical data.
Consumables Provide basis to be used in estimating consumables and refer to any definition of
consumables including differentiation with "construction aids" which tend to be consumable over the life
of a long project but re-usable within that time. E.g.; tarps, rope, etc.
Craft Benefits and Burdens - Normally part of the craft wage rate build-up but may be separately
identified if required by the owner or contractor estimating methodology and execution strategy. Obtain a
copy of the craft labor agreements for determining benefits and special conditions such as: mileage
payments, health care expenses, payroll taxes, workers compensation, etc.
General Demolition
This addresses general demolition of decommissioned and/or abandoned facilities. Demolition for
revamps is typically included with each commodity/discipline. Describe the general demolition scope and
RPRP
Copyright 2009 AACE International, Inc.
AACE International Recommended Practices
Development of Cost Estimate Plans As Applied in Engineering, Procurement, and
Construction for the Process Industries
June 12, 2009
12 of 24
how it will be estimated. Where possible, it should be based on field-verified quantities and quoted
subcontract rates. The owner should provide any direction required on treatment of expense versus
capital for demolition.
Commissioning and Start-Up
Explain how commissioning and start-up costs will be determined and briefly describe the related scope
(e.g.: crew-based, factored from historical data, etc.) Refer to owner-approved definition of mechanical
completion to distinguish between commissioning work and construction work. Reference spares
discussion above. Quantities of initial fills of lube oil, heating/cooling mediums, chemicals, etc. to be
estimated by process group based on equipment sizing, vendor information, and process conditions.
Catalyst and packing pricing may be based on discussions with licensors, engineering contractors, and
vendors.
Engineering and Home Office Hours
For each discipline, describe how the labor hours will be determined (e.g.: deliverables, commodity
quantities, time-based, etc.) Estimating of work week and overtime for head office personnel should be
discussed. Include construction support to home office, home office support to construction, engineering
site visits, vendor shop inspections, start-up support, preparation of operating manuals, engineering
services such as reliability and maintainability (RAM) studies, heavy lift studies (if applicable),
environmental consultants, HAZOP (hazardous operations reviews) facilitators, constructability
consultants, module coordinators, etc. State whether field engineering and site based "as-built drafting"
work are included with construction indirect costs. Project management may be separately addressed
depending on how the cost account structure is organized.
Engineering and Home Office Costs
Show how the engineering labor rates are to be built-up. Describe how other office costs and fees will be
covered and refer to any contracts in place. Identify prior project phases to be included in the estimate
such as front end loading 2 (FEL2) and FEL3.
Clarifications, Qualifications and Assumptions (to be included under discussion of each commodity or in
general)
Clarifications and assumptions which apply to more than one commodity or are more effectively identified
separately are addressed in this section. The rationale for any assumptions to be used should be
provided. Consider the items in Appendix D which are often omitted but should be clarified. This section
may be combined with Exclusions.
Exclusions
Contractors often state anything not specifically identified is assumed to be out of scope. Owners assume
everything required is included in contractor estimates unless they have specified otherwise. Neither
approach provides sufficient information to prepare a good estimate. All known estimate exclusions
should be listed with an explanation of why. For example:
Financing charges will not be included because they will not be allocated back to the project.
Operating and maintenance spares are excluded. They will be purchased by operations.
Recoverable taxes and duties are excluded (identify which taxes e.g.: sales tax.) These costs will
be paid by the project but credited upon recovery.
RPRP
Copyright 2009 AACE International, Inc.
AACE International Recommended Practices
Development of Cost Estimate Plans As Applied in Engineering, Procurement, and
Construction for the Process Industries
June 12, 2009
13 of 24
Owner Costs
Do not create a separate section for owner costs. Owners may execute all of the project scope or none
and all options in between. Therefore, owner scope should be addressed in the appropriate section of
estimate plans or clarified in contractor estimate plans by listing each specific owner scope item
excluded. Refer to Appendix H for typical items to be clarified for each estimate.
Late Changes
Explain how late changes subsequent to the estimate cut-off date will be handled. A log should be kept of
all changes and integrated with the project change management procedures. The log will be part of the
estimate package. Consider any owner formatting requirements for late changes.
Escalation
Include a description of escalation calculations and sources. As a minimum it should be broken down into
the major categories of equipment, bulk material, construction labor, and engineering. Known wage rate
increases after the point in time of the estimate basis are covered by escalation and should not be
included in the base estimate to maintain consistency.
Risk Analysis and Recommended Contingency
Contingency is typically recommended by contractors but determined by owner management based
primarily on the results of the cost estimate and schedule risk analyses. State the software and
methodology to be used. A different contingency may be appropriate for each process unit or area of the
facility due to varying levels of definition and confidence in the base estimate. A summary of the risk
analyses results should be included in a separate section of the basis of estimate with a cost risk profile
chart. The chart should show the P10, P50, expected value and P90 points on the curve or other points
specified by the owner. On larger projects, a tornado diagram showing the top ten risks and opportunities
may be included.
Benchmarking
As part of the estimate review and validation process, benchmarking should be performed. The intended
source(s) of benchmark data is stated as well as the metrics to be used in benchmarking. Key metrics
should be included with the estimate basis for quick reference. These will vary depending on the class of
estimate. Refer to Appendix E for an example list of metrics.
Cash Flow/Cost Flow
Provide a sample cash flow in table format according to the intervals required by the owner (monthly,
quarterly, etc.) Describe how the cash flow will be determined for each category breakdown such as:
historical data, project-specific progress and manpower profiles, standard payment terms, etc.
Estimate Development Schedule
The estimate development schedule should be an integral part of the project schedule for the applicable
phase. For large projects, it will be within a CPM schedule which can be used for integrating the estimate
plan with other phase deliverables and for tracking. This approach keeps focus on the engineering and
execution development activities required to meet the objectives for that phase and the desired estimate
RPRP
Copyright 2009 AACE International, Inc.
AACE International Recommended Practices
Development of Cost Estimate Plans As Applied in Engineering, Procurement, and
Construction for the Process Industries
June 12, 2009
14 of 24
accuracy. AACE International RP 18R-97 (Cost Estimate Classification System As Applied In
Engineering, Procurement, And Construction For The Process Industries)[7] provides a summarized
estimate input checklist and maturity matrix. A detailed estimate development schedule is produced to
show the timing of activities required. Refer to Appendix F for example list of activities shown in no
particular order.
Estimate Responsibility Matrix
An estimate responsibility matrix is a useful tool in planning and managing the key estimating
deliverables. Develop a matrix indicating which documents will be used in the estimating process, who
will provide them (including organization), the expected level of completion (i.e.: preliminary, IFD, etc.)
and the date. The matrix can be an extract from the project schedule or in spreadsheet format. Providing
contact information for each person shown in the matrix is helpful. Refer to Appendix G for an example
matrix. An improvement to this format would be to add a column for who will estimate the items.
REFERENCES
1. Kinney, Christopher L., Planning the Development of Your Estimate!, 2006 AACE International
Transactions, AACE International, Morgantown, WV, 2006.
2. Williams, David A., The Estimate Preparation Plan, AACE International Chinook-Calgary Section
newsletter, January 2008.
3. AACE International Recommended Practice No. 19R-97 Estimate Preparation Costs As Applied
For The Process Industries, AACE International, Morgantown, WV, (latest revision).
4. Hollmann, John K., Editor, Total Cost Management Framework: An Integrated Approach to Portfolio,
Program, and Project Management, AACE International, Morgantown WV, 2006.
5. AACE International Recommended Practice No. 10S-90 Cost Engineering Terminology, AACE
International, Morgantown, WV, (latest revision).
6. AACE International Recommended Practice No. 34R-05 Basis of Estimate, AACE International,
Morgantown, WV, (latest revision).
7. AACE International Recommended Practice No. 18R-97 Cost Estimate Classification System As
Applied In Engineering, Procurement, And Construction For The Process Industries, AACE
International, Morgantown, WV, (latest revision).
CONTRIBUTORS
Gregory C. Sillak (Author)
Bruce E. Bradley
Keith R. Didriksen
Fabiana Francis, PSP
Dr. Paul D. Giammalvo, CCE
Ambrish Gupta
John K. Hollmann, PE CCE CEP
Carlton W. Karlik, PE CEP
Christopher L. Kinney
Paul S. Kupakuwana
Paratharajan N. Pille
L. Ron Rowland
Terence M. Stackpole
T. Mac Sumrall, CCC
David A. Williams, CEP
Charles P. Woodward, PE CCE CEP
Joseph Yang, CCE
Nor Y. Yazid
James G. Zack, Jr. CFCC
RPRP
Copyright 2009 AACE International, Inc.
AACE International Recommended Practices
Development of Cost Estimate Plans As Applied in Engineering, Procurement, and
Construction for the Process Industries
June 12, 2009
15 of 24
APPENDICES
APPENDIX A Example Table of Allowances
Commodity
Design/Material Take-Off
(MTO) Allowance
Construction Waste Allowance
Earthwork
10%
12%
Site Work
12%
10%
Piling Drilled Caisson
5%
7%
Piling Sheet
3%
1%
Concrete
7%
10%
Steel Fabrication
8%
10%
Steel Module
8%-10%
15%
Steel Stick-Build
5%-10%
12%
Architectural/Buildings
6%-10%
8%
Equipment
5%
0%
Piping Fabrication
5%-10%
10%
Piping Module
5%-10%
10%
Piping Stick-Build
5%-10%
10%
Steam Tracing
15%
8%
Electrical Equipment
5%
0%
Electrical Tray/Conduit
10-20%
10%
Electrical Wire/Cable
10-20%
15%
Electrical Heat Tracing
15-30%
5-20%
Instrument Control Valves
5-15%
0%
Instrumentation Panels/Racks
5-10%
0%
Instrumentation Tubing
10-30%
10%
Instrumentation Instruments
5-15%
0%
Insulation Piping
10-30%
10%
Insulation Equipment
5-15%
10%
Fireproofing Equipment
Fireproofing Steel
15-25%
5%
Painting
10-25%
3%
RPRP
Copyright 2009 AACE International, Inc.
AACE International Recommended Practices
Development of Cost Estimate Plans As Applied in Engineering, Procurement, and
Construction for the Process Industries
June 12, 2009
16 of 24
APPENDIX B Example Summary Format for Quantity Take-Off and Pricing
Commodity/Activity
Take-Off Method
Pricing Method
Earthwork
Quoted subcontract rates.
Site Work
Quoted unit rates.
Hydrovac
Quoted day rate.
Piling
Quoted unit rates.
Concrete
Civil design drawings,
vendors shop drawings and
soil tests.
Quoted rates for materials
and/or subcontracts.
Steel
Architectural/Buildings
Quoted subcontract rates.
Equipment
Equipment list.
80% budget quotes.
Piping
Supplied by piping
engineering.
Heat Tracing
Heat tracing and insulation
specifications, piping take-
offs and vendor quotations.
Steam supply and
condensate return headers
are to be estimated based on
heat load requirements and in
accordance with company
specifications.
Electrical Equipment
Formal vendor quotations.
Electrical Tray/Conduit
Supplied by electrical
engineering department.
Quoted subcontractor rates
for labor, materials, field
indirects and contractor
overhead and profit.
Electrical Wire/Cable
Supplied by electrical
engineering department.
Quoted subcontractor rates
for labor, materials, field
indirects and contractor
overhead and profit.
Electrical Heat Tracing
Averaged from samples and
quantified by line list.
Subcontractor budget quote
with allowance.
Instrument Control Valves
Count from P&IDs.
Instrumentation Panels/Racks
I/O count.
Instrumentation Tubing
Factored from tagged item
count.
Instrumentation Instruments
Tagged item and I/O count.
Insulation Piping
Supplied by piping
engineering. Allowances for
valves, fittings and specialties
based on the equivalent
length method.
Quoted subcontract unit
rates.
Insulation Equipment
Fireproofing Equipment
Fireproofing Steel
Painting
Scaffolding
Factored from direct labor
accounts.
RPRP
Copyright 2009 AACE International, Inc.
AACE International Recommended Practices
Development of Cost Estimate Plans As Applied in Engineering, Procurement, and
Construction for the Process Industries
June 12, 2009
17 of 24
APPENDIX C Examples of Planned Bulk Material Quantity Basis
Earthwork and Site Work Reference geotechnical data, topographical drawings, or photogrammetric
maps, to be used. State whether tree/brush clearing/grubbing is required in addition to topsoil removal
and general cut and fill operations to level site. Explain whether excavation and backfill quantities are to
be developed from standard foundation details, underground trench sketches, or other method. E.g.,
dewatering for excavation of permanent facilities will be a percentage of excavation of backfill quantities.
Address whether quantities will be generated for permanent fencing, signage, and landscaping and how.
Similarly discuss road, railway, and marine work.
Piling Explain how quantities are determined for each type of pile. E.g., diameter and depth for drilled
caissons. Include any clarifications for quantifying rebar, aggregate, sonotube, etc.
Concrete Reference any standard foundation designs which may exist and describe how quantities are
developed for cast in place concrete formwork, insulation, aggregate, embeds (rebar, anchor bolting,
etc.) Also address specialty items such as curing agents or cementitious grout. Explain any strategies
regarding quantities of pre-cast concrete whether purchased or precast at site. Reusable forms may be
addressed here or in indirects depending on the code of accounts in effect.
Structural Steel Separate module assembly quantities from site-installed quantities. If MTO's are
desired by light, medium and heavy this needs to be stated. Define whether tube-shape pipe supports
are part of piping quantities or structural steel account.
Buildings Sizing basis such as equipment layouts/sizes shown on issue for design (IFD) revision of plot
plan. Determine extent of furnishings and fixtures included for each building as well as single or multiple
floors. Categorize buildings as process, electrical, maintenance shops, warehouse/storage or
administration for estimating and financial treatment.
Piping Define the sizes included in small bore versus large bore piping (e.g., >2") and criteria for
physical allocation of bulk material across more than one process unit (e.g., 1st valve downstream,
exactly at battery limit coordinates, etc.) Reference specifications, P&ID's, plot plans, and routing basis
used for determining lengths. State that steam trace tubing length calculation basis excludes "hard piped"
supply/return lines and headers for clarity. Provide rationale for factors to be used in determining steam
tracing, small bore, shoes, guides and hangers.
Electrical State expected use of equipment load list, single line diagram and area classifications. If
instrument wiring is part electrical account, include basis such as I/O count, instrument count and routing
used for determining lengths. Refer to wire and cable specifications. State junction box location
assumptions for quantifying terminations. Electric heat tracing specifications should state how equipment
and piping (by pipe spec/size) affect tracer type and routing as well as controllers.
Instrumentation Identify revision of P&ID's to be used for instrument counts, control systems, panels,
etc. Clarify whether items shown on P&ID's within vendor packages are part of vendor pricing and extent
to which the related wiring or tubing are part of vendor packages. If vendor supplied, state if already
installed in "package" (only requiring testing & calibration where applicable) or if vendor supplied but
shipped loose, for contractor to install. All other quantities are assumed to be required from vendor skid
back to control points or junction boxes. State the basis for any allowances for installed spares and spare
card slots. Sizing of control systems may be from I/O count or vendor.
RPRP
Copyright 2009 AACE International, Inc.
AACE International Recommended Practices
Development of Cost Estimate Plans As Applied in Engineering, Procurement, and
Construction for the Process Industries
June 12, 2009
18 of 24
Painting State how field and touch-up painting will be quantified (e.g., factored based on historical
data.)
Fireproofing Explain whether any structural steel or vessel fireproofing is required and if it will be
applied at site or in vendor's shop or at site. Outline how any site cast fireproofing will be quantified.
Insulation Describe the methods to be used for equipment and pipe insulation with reference to
specifications (blanket, formed, material, jacket, removable, valve/flange covers, etc.)
RPRP
Copyright 2009 AACE International, Inc.
AACE International Recommended Practices
Development of Cost Estimate Plans As Applied in Engineering, Procurement, and
Construction for the Process Industries
June 12, 2009
19 of 24
APPENDIX D Examples of Clarifications, Qualifications and Assumptions
Direct Site Costs
Interface with 3rd party suppliers, contractor interfaces, fabricators, and vendor reps.
Special comments regarding specifications. E.g., calcium silicate versus mineral wool insulation.
Lack of engineering and design clarity. For instance if soil borings were not available.
Indirect Site Costs
Availability of space for parking at construction site or bus pick-up locations.
Any known interactions with other projects and operating facilities for roads, access, emergency
response, resource availability, hazardous environments, evacuation, etc.
Allowances for emergency evacuations.
Offloading facilities.
General Site Costs
Jobsite access restrictions/expectations.
Availability of permanent facilities to be used for construction purposes including timing for owner
use. E.g.: admin building, storage, paved areas.
Use of any existing facilities/equipment for the current project (construction or permanent.)
Assumptions for calculations used. E.g., Load-carrying capacity of existing
structures/buildings/pipe-racks.
Who is responsible for EP&C of the electrical substation, electrical feeders, etc.
Hot and cold work permitting requirements and procedures.
Lighting and power requirements around new equipment, temporary facilities and construction
parking.
Transportation infrastructure for large shipments and modules. Includes road repairs.
Approach to shop fabrication and field erection to minimize field labor, to allow for greater quality
control, and to minimize schedule disruptions.
Procurement, Fabrication and Offsite Assembly
Extent of offsite fabrication for each commodity.
Determination of commodities to be included with module assembly versus "stick-build".
Degree of shop inspection (e.g.: heavy to avoid field rework, or normal to low risk due to owner
alliance with vendors.)
General Project Costs and Overheads
Purchase of operations or maintenance equipment.
Separately identify pre-investment cost of future facilities including pro-rata share of
civil/structural.
Environmental and regulatory permitting fees.
Known and unknown environmental issues such as contaminated soil, lead, asbestos, etc.
Licensor fees, licensor engineering, licensor royalties.
Reimbursable versus non-reimbursable costs.
Assumed to be capital cost except where owner has otherwise specified.
Non-recoverable taxes are included. (Identify which taxes.) They will be paid by the project.
Non-recoverable duties are included. They will be paid by the project.
Owner to confirm if wasted/consumed feedstock or spoiled product cost will be charged to the
project.
RPRP
Copyright 2009 AACE International, Inc.
AACE International Recommended Practices
Development of Cost Estimate Plans As Applied in Engineering, Procurement, and
Construction for the Process Industries
June 12, 2009
20 of 24
APPENDIX E Examples of Key Metrics
Hours per Quantity (by commodity)
Detailed Engineering Cost / Total Project Cost (TPC)
Construction Management Cost / TPC
Bulk Material Cost / TPC
Construction Labor Cost / TPC (construction labor includes indirect labor)
Construction Direct Labor Cost / TPC
Construction Indirects / TPC
Total Field Material Cost / TPC (field material includes equipment, bulks and domestic freight)
Total Field Costs / TPC
Start-Up / TPC
TPC / Total Equipment Cost (excludes equipment installation)
Detailed Engineering / Total Equipment Cost (excludes equipment installation)
Construction Labor Cost / Total Equipment Cost (excludes equipment installation)
Construction Indirects / Total Equipment Cost (excludes equipment installation)
Total Field Labor / Total Equipment Cost (excludes equipment installation)
Total Field Cost / Total Equipment Cost (excludes equipment installation)
Start-Up Cost / Total Equipment Cost (excludes equipment installation)
Engineering hours per piece of equipment
Engineering hours per quantity of material by discipline
Engineering all-in rate per hour
Ratio of bulk material cost to equipment cost
All-in construction rate [total labor cost + indirect cost] / [direct labor hours including
subcontractor hours]
Percent scaffold labor of direct labor hours including subcontractors
Percent offsite fabrication hours and construction hours of total hours by commodity
RPRP
Copyright 2009 AACE International, Inc.
AACE International Recommended Practices
Development of Cost Estimate Plans As Applied in Engineering, Procurement, and
Construction for the Process Industries
June 12, 2009
21 of 24
APPENDIX F Examples of Activities to Include in the Estimate Development Schedule
Develop and finalize estimate plan
Place long lead PO's
Incorporate COMPANY specifications
Obtain quotes for equipment
Obtain pricing for bulk materials
Calibrate estimating databases and systems as required
Confirm level of engineering and execution definition required to meet estimate accuracy with
key personnel
Finalize estimate deliverable responsibility matrix
HAZOP reviews complete
Develop execution phase coding and control structure
Determine productivity factors
Determine construction labor wage rates
Determine engineering wage rates
Determine basis for calculating design and material allowances
Prepare project execution plan
Preliminary start-up sequence
Clarify scope elements to be estimated by owner and/or contractor
Construction labor productivity rates
Construction labor wage rate build-up
Subcontract pricing methodology
Material, equipment, and fabrication pricing
Construction indirect estimating methodology
Engineering estimate methodology (hours, labor rates, services, expenses, fees, profit, other
"home office" costs)
Estimate coding and formatting for development, review, and control
Develop execution schedule and resource loading
Constructability review
Freeze process basis for estimate
Freeze scope development basis estimate including plot plan
Freeze execution basis for estimate
Obtain input from vendors, subcontractors, and fabricators
Estimate engineering hours and costs
Estimate bulk material costs
Estimate equipment costs
Estimate construction labor hours and costs
Estimate fabrication hours and costs
Determine construction indirect costs
Estimate escalation
Incorporate late changes
Perform risk analysis and contingency recommendation
Incorporate activities of risk consultants if applicable
Prepare cash flow
Calculate key cost estimate metrics
Complete cost estimate basis
Prepare for cost estimate reviews
Owner estimating/project controls review of cost estimate
Owner project management review of cost estimate
Owner cost estimate and gate approval
RPRP
Copyright 2009 AACE International, Inc.
AACE International Recommended Practices
Development of Cost Estimate Plans As Applied in Engineering, Procurement, and
Construction for the Process Industries
June 12, 2009
22 of 24
APPENDIX G Example Estimate Responsibility Matrix Format (Adapted from RP 18R-97[7])
Document
Rev.
Level of
Completion
Estimating
Responsibility
Source
Information
Date
Project Scope Description
Defined
PM
Owner PM
Production Capacity
Defined
Process
Process
Engineer
Plant Location
Specific
PM
Owner PM
Soils & Hydrology
Defined
Civil Engineer
Owner Civil
Engineer
Project Execution Plan
Defined
Project Master Schedule
Defined
Start-Up Sequence
Preliminary
Escalation Strategy
Defined
Work Breakdown Structure
Defined
Project Code of Accounts
Defined
Contracting Strategy
Defined
Subcontracting Plan
Defined
Constr. Work Packages
Complete or Near
Constr. Mgmt Manpower
Defined
Construction Indirects
Defined
Scaffolding
Factored
Construction Productivity
(expand by commodity if
applicable)
Defined
Construction Wage Rates (by
discipline)
Defined
Engineering Hours by Discipline
Factored
Engineering Wage Rates
Defined
PM & Support Hours
Factored
PM & Support Wage Rates
Defined
ODC & FEE
Per Contract
Block Flow Diagrams
Complete
Plot Plans
Complete or Near
Process Flow Diagrams
Complete or Near
Utility Flow Diagrams
Complete or Near
P&ID's
Complete or Near
Line List
Complete or Near
Tie-In List
Complete or Near
Heat & Material Balances
Complete or Near
Process Equipment List
Complete or Near
Utility Equipment List
Complete or Near
MTO's (by each commodity)
Partial
Instrument Index
Complete or Near
Instrument Allowance
Factored
Electrical One-Line Drawings
Complete or Near
Spec's & Datasheets
Complete or Near
General Arrangement Drawings
Complete or Near
Spare Parts List
Started or Partial
Mechanical Discipline Drawings
Started/Sketches
Electrical Discipline Drawings
Started/Sketches
Instrumentation/Control System
Discipline Drawings
Started/Sketches
Civil/Site Discipline Drawings
Started/Sketches
Structural Discipline Drawings
Started/Sketches
RPRP
Copyright 2009 AACE International, Inc.
AACE International Recommended Practices
Development of Cost Estimate Plans As Applied in Engineering, Procurement, and
Construction for the Process Industries
June 12, 2009
23 of 24
APPENDIX H Checklist of Potential Owner Cost Items
Direct Costs
Breakdown as per normal for direct costs (owner is a resource like a contractor or subcontractor)
Construction Indirect costs
Breakdown as normal for indirect costs
Owner construction management staff (construction supervision, safety, field engineering,
warehousing/material control, operations support)
Personal protective equipment and clothing. E.g.: hard hats, boots, fire retardant suits, etc.
(clarify whether owner supplies any of these for contractors or vice versa)
Cranes, scaffolding, tools, construction services, drinking water, etc.
Demolition (if not included above)
Project Management Staff and Expenses
Project management (breakdown and include project controls, accounting,
procurement/contracts, admin, document control, travel, contractors, consultants, etc.)
Project Engineering and Design (breakdown by discipline)
Owner direct hire staff and expense
External contractors/services hired by owner (excluding EPC, EPCM, prime contractor, etc.)
Licensor engineering development and design not included in licensor fees or royalties
Specification writing/purchase, if required
Operations Staff and Expenses
Permitting (daily construction hot and cold work permits)
Design reviews
Facility shutdown/start-up costs if charged to project (e.g.: for blinding, purging, steaming,
flushing, etc.)
Commissioning and Start-Up
Staff and contractors organization
Services and consultants
Materials and supplies
Equipment and tool rentals
Initial feedstock costs and process waste costs, if applicable
Lubricants, chemicals, dessicants, etc.
Information Technology (leased versus purchased to be considered)
Network infrastructure and telecommunications
Desktop hardware
Standard desktop software
Special software applications (Primavera, CAD, document control, etc.)
Radio towers, base stations and licensing (radios can be here or indirects if rented)
RPRP
Copyright 2009 AACE International, Inc.
AACE International Recommended Practices
Development of Cost Estimate Plans As Applied in Engineering, Procurement, and
Construction for the Process Industries
June 12, 2009
24 of 24
Land
Land purchase only - rental/lease cost during project should be indirect construction cost
Project Overheads
Regulatory process and approvals
Public relations and promotional events
Right of way access and permits with governments and/or landowners
Licensor fees, licensor royalties
Insurance premiums and allowances for deductible occurrences
Financing and interest charges
Foreign exchange costs not captured by specific purchase or contract item
Currency hedging costs charged to project
Corporate overhead allocations
Property taxes (if paid during construction)
Legal services
Non-recoverable duties should be charged to the individual foreign-purchased items and
recoverable duties should be credited to the individual items
Training of and development of local citizens on international projects
Purchased Assets (if not treated as a direct or indirect)
Spares (capital, start-up, operating)
Initial stores stock
Furniture - if not covered within buildings account
Mobile equipment
Catalyst and chemicals if not covered elsewhere
Capital Contributions to Utility Infrastructure or 3rd Party Facilities
Power/electricity
Water supply
Gas
Waste/effluent disposal, water treatment
Process units (e.g., hydrogen plant)
Environmental Remediation and Monitoring
Contaminated/hazardous soil excavation and clean-up
Hauling and disposal costs
Monitoring (air, soil, water)
Asbestos and lead paint removal
International Freight
International freight and related costs, including taxes and duties, should be captured with the
items where possible. This allows accurate cost comparison versus more local sourcing. Special
tracking codes may be required for separation of asset values versus related shipping costs.